Operational acceptance


Every development that is required to obtain a certificate of Operational Acceptance needs to meet the following criteria.

Operational Acceptance submission steps. Step 1. Once construction of the development is completed, the applicants prepare and lodge an Operational Acceptance submission through the ProjectWise portal. Step 2. TCCS assesses the submission against the original design. If the submission meets the TCCS requirements, a Certificate of Operational Acceptance will be issued. If amendments are required, the applicants will be advised in writing by TCCS.  All re-submissions should be done via  the ProjectWise portal.  Step 3. If required, applicants can apply for a Soft Landscape Consolidation Commencement via the ProjectWise portal.  If the submission meets the TCCS requirements a Certificate of Soft Landscape Consolidation  Commencement is issued.

Lodgement of Operational Acceptance submissions

All post DA submissions must be lodged via the ProjectWise Portal as per the process (PDF 252.4 KB).

Users with valid licences can login remotely to the ProjectWise and Summary Works as Executed (WAE) portals from this page on a 24/7 basis.

To obtain a licence to use the portals or for other enquiries regarding the portals, please contact TCCS.ProjectWiseAccounts@act.gov.au

Please review here for information relating to the Ref 11 Drafting Standard and Ref 11 Toolkit.

All development submissions

When lodging an Operational Acceptance submission please note the following important requirements:

Assessment process

  1. Consultant lodges the submission as per above document requirements. Submissions from individual consultants for separate elements of work for the same project and in the same location must be presented together.
  2. We undertakes a content check to ensure the minimum requirement for lodgement of Operational Acceptance submission is met. An acknowledgement email will be issued the day the submission is received. Submissions received after 12pm will receive an acknowledgment email the next business day. Incomplete submissions and those which do not meet all the requirements are returned to the consultant for completion.
  3. If the Operational Acceptance submission has met all the requirements, an inspection is arranged to assess works as constructed.
  4. If works are satisfactorily completed, we will issue the certificate of Operational Acceptance.

Fees and charges

Fees and charges may apply for repeat applications, submissions and inspections of works. Please refer to the Submissions and Inspections Guideline Principles and Related Fees and Charges (PDF 338.1 KB.

More information on the asset assessment process can be found on the Asset assessment page.