Early works and design review


End of year submission cut off dates for 2026

We would like to provide the following advice to assist you in managing your lodgements and obtaining an outcome or certificate before the Christmas shutdown period, as outlined in the email to the industry issued on Thursday 8 October 2026:

  • Design Review (DR), Operational Acceptance (OA), Soft Landscape Consolidation Commencement (SLCC), Soft Landscape Handover (SLH) and Final Acceptance (FA) submissions should be lodged via ProjectWise prior to COB Friday 20 November 2026.
  • Operational Acceptance (OA) submissions* which include playgrounds, barbeques, bins, bubblers, and other contract / programmed maintenance items should be lodged via ProjectWise by COB Friday 6 November 2026.
  • Soft Landscape Handover (SLH) submissions* which include areas of open space, playgrounds, playing fields or irrigation should be lodged via ProjectWise by COB Friday 6 November 2026.
  • Development Application (DA) and Building Applications (BA) for Driveway, Stormwater and LMPP can be lodged via eDevelopment / smart form at any time. However, responses and timeframes will be paused between Monday 21 December 2026 to Sunday 10 January 2027**.

*The above scheduling is to ensure the sufficient time to arrange the inclusion of these elements on the maintenance programme of CED and their contractors.

**This is to align with Section 192 of the Planning Act 2023. Under Section 192 a ‘working day’ is any day that’s not a Saturday or Sunday, public holiday or between 20 December and 10 January (inclusive).

Please note we will make every effort to meet the target dates, however this may be subject to the volume of submissions received (particularly in the 2 weeks prior to Christmas shutdown) and the resource capacity availability. We will notify you accordingly and appreciate your support should we not be able to meet the targets.

From January 2026, applicants may opt out of Design Review for the following activities:

  • Driveways crossing a verge
  • Stormwater ties
  • Kerbside residential waste collection / onsite commercial waste collection
  • Footpaths
  • Streetlight relocation up to 5 m
  • Trees planted within grassed / organic street verges (paved areas are excluded)

Applicants who opt out will not receive a Letter of Design Review (LoDR). Early Works Approval is waived. Asset Acceptance and COOU can proceed without LoDR. Engineering certification remains mandatory, by way of the certification forms:

Any comments of feedback on the changes can be sent to via email to CED.dcdevelopmentcoordination@act.gov.au.

Every development that is required to obtain a Letter of Design Review needs to meet the following criteria.

Flow chart showing the 4 steps involved in the Design Review process

Early works submissions

Early works submissions can be requested ahead of lodging a formal Design Review submission to the Design Review and Asset Acceptance (DRAA) team to commence preliminary construction activities, such as:

  • Demolition
  • Clearing and grubbing
  • Earth works

Early works submissions may be requested if there is a need to commence these preliminary construction activities after obtaining a Notice of Decision. These approvals are issued by DRAA and the normal approval time is 10 working days.

Early works submissions should be lodged via the ProjectWise Portal. Please be aware fees and charges apply for all early works submissions.

Lodgement of Design Review submissions

All post DA submissions must be lodged by the Consultant for the development via the ProjectWise Portal as per the process (PDF 1.0 MB).

Users with valid licences can login remotely to the ProjectWise and Summary Works as Executed portals from this page on a 24/7 basis.

To obtain a licence to use the portals or for other enquiries regarding the portals, please contact TCCS.ProjectWiseAccounts@act.gov.au.

Please review here for information relating to the Ref 11 Drafting Standard and Ref 11 Toolkit.

Single block, infill developments

These requirements should be used for infill, residential and/or commercial developments within a single block. It specifically excludes developments which require subdivisions, or the creation of new infrastructure networks.

When lodging a Design Review submission please note the following requirements:

  1. Documentation as per Ref 06A Requirements for design review submission - infill developments (PDF 1.0 MB)
  2. Ref 06A - Design Review submission cover sheet for infill developments (PDF 623.1 KB)
  3. TCD transmittal form (if applicable)
  4. Waste and Recycling Management Plan (EXL 190.5 KB)

All other development submissions

When lodging a Design Review submission please note the following important requirements:

  1. Documentation as per Reference Document 6 (PDF 1.3 MB)
  2. Ref 06 - Design Review submission cover sheet (PDF 1.3 MB)
  3. TCD transmittal form (if applicable)
  4. Waste and Recycling Management Plan (EXL 190.5 KB)

Assessment process

The Design Review process includes the following steps:

  1. Consultant lodges the submission as per above document requirements. Submissions from individual consultants for separate elements of work for the same project and in the same location must be presented together.
  2. We undertake a content check to ensure the minimum requirements for lodgement of a Design Review submission is met. An acknowledgement email will be issued the same day for submissions received prior to 12 pm each business day. Submissions received after 12 pm will receive an acknowledgment email the next business day.
  3. Incomplete submissions and those which do not meet all the requirements are returned to the consultant for completion.
  4. The Directorate issues a Letter of Design Review once all requirements are met.

Fees and charges

Fees and charges may apply for repeat applications, submissions, and inspections of works. Please refer to Submissions and Inspections Guideline Principles and Related Fees and Charges (PDF 338.1 KB).

More information on the asset assessment process can be found on the Asset assessment page.

Contact us

Please contact us via email if you have any questions.