Project description
A new pedestrian and cycle path has been constructed along the eastern side of Flemington Road between Well Station Drive and EPIC. This new path will provide better and safer access between Franklin and Mitchell, particularly to and from the Mitchell commercial precinct and the light rail stops.
In addition to the path works, lighting and signage, more than 100 trees were planted along the length of the project.
Stage 1: EPIC to Morisset Road
Construction
- Start date: November 2019
- Completion date: June 2020
Stage 2: Morisset Road to Well Station Drive
In addition to the path works, this stage of the project saw the planting of more than 100 trees.
Construction
- Start date: March 2020
- Completion date: June 2020