Construction: Stage 1
In the 2023-24 ACT Budget, the ACT Government matched the $5 million committed by the Australian Government for detailed design and construction of the first stage of the route. This includes segments one to four identified in the preliminary stage of design, which includes the connections between the City and Braddon from Cooyong Street, along Torrens and Ijong streets and along Angas Street to Majura Avenue.
Stage 1 has been split into 4 sub-stages as follows:
- A. Torrens Street between Cooyong Street and Ipima Street
- B. Torrens Street from Ipima Street to Ijong Street and along Ijong Street to Limestone Avenue
- C. Angas Street between Limestone Avenue and Majura Avenue
- D. Cooyong Street.
1A (complete): Torrens Street between Cooyong Street and Ipima Street
This was the first part of the cycleway constructed. It includes a new 4-metre-wide concrete and asphalt walking and cycling path in the eastern verge of Torrens Street, from Cooyong Street to Henty Street and a new 3-metre-wide path will continue from Henty Street to Ijong Street in Braddon.
Where the cycleway crossed driveways, the driveway was treated with line marking to alert users to the driveway crossing point.
In addition, 6 new raised asphalt zebra crossings were constructed along the cycleway at the crossing points on Torrens Street (near Cooyong Street), Elouera Street, Girrahween Street, Henty Street, Helemon Street and Ipima Street.
You can take a look at the detailed drawing (PDF 3.6 MB).
1B (complete): Torrens Street from Ipima Street to Ijong Street and along Ijong Street to Limestone Avenue
This was the second part of the cycleway constructed. It includes a new 3-metre-wide asphalt walking and cycling path in the eastern verge of Torrens Street and Ijong Street.
Where the path crosses driveways, sections of the driveway were treated with line marking to alert users of the driveway crossing point.
In addition, new traffic lights were installed at the Limestone Avenue, Ijong Street and Angas Street intersection.
You can take a look at the detailed drawing (PDF 1.8 MB)
1C (complete): Angas Street from Limestone Avenue to Majura Avenue
This was the third part of the cycleway constructed. It includes a new 3-metre-wide asphalt walking and cycling path in the eastern verge at the start of Angas Street then crossing to the western verge and continuing to Majura Avenue.
Where the path crosses driveways, sections of the driveway have been treated with pavement marking and line marking to alert of the driveway crossing point.
In addition, 4 raised concrete zebra crossings have been constructed along the cycleway at the crossing points on Angas Street, Wakefield Avenue and at the Ainslie district playing fields car park entry and exit.
You can take a look at the detailed drawing (PDF 7.1 MB).
1D (construction commencing): Cooyong Street between Torrens Street and Lonsdale Street
Construction is expected to begin in the week commencing 25 May 2026 to deliver Stage 1D of the Garden City Cycleway. Stage 1D runs along Cooyong Street between Londsdale Street and Torrens Street.
Works to deliver Stage 1D are expected to take 6 months to complete, weather and site conditions permitting.
Stage 1D comprises the removal of the existing concrete path and construction of a new 3-metre-wide concrete walking and cycling path in the northern verge of Cooyong Street between Lonsdale Street and Torrens Street. The Garden City Cycleway terminates at the intersection of Lonsdale Street and Cooyong Street where users can safely cross Cooyong Street and connect to the Bunda Street shared zone.
Works will be largely completed outside peak hours between 9:30 am to 4:00 pm or 6.30 pm to 10:00 pm Monday to Friday. At times, if required, works may be carried out during the same hours on weekends.
Construction will be carefully staged to minimise community impacts and limit traffic congestion. Works will begin with a new kerb ramp on the southern verge of Cooyong Steet/ Genge Street, then modifications to the Cooyong Street median island, followed by the main work in the northern verge of Cooyong Street.
There will be temporary lane closures in both directions on Cooyong Street and a road closure between Lonsdale Street and Torrens Street. A separate road closure on Torrens Street will also be required. However, lane and road closures will be programmed to minimise disruption wherever possible.
Construction activities across driveways will require temporary changes to accommodate works. However, access to the service station will be maintained throughout the project. Alternative access will be facilitated as required. The contractor will be in touch with impacted businesses and residents where driveways are impacted.
Pedestrian detours will also be in place and signage will be installed to safely detour pedestrians and cyclists around the works.
The Garden City Cycleway terminates at the intersection of Lonsdale Street and Cooyong Street where users can safely cross Cooyong Street and connect to the Bunda Street shared zone. The City Renewal Authority is progressing the design of upgrades to Cooyong Street. This work will refer to the design work undertaken by the Garden City Cycleway design team.