Construction
Initial works have started on site including installation of the site compound which will be located on the grassed area between Club Lime and Moby Dicks Tavern adjacent the existing driveway. Construction is expected to take approximately 9 months to complete, weather permitting. To minimise impacts on businesses and the local community, works will be staged (see map below). We will be working to complete the most disruptive works ahead of the Christmas trade period. Works will be carried out as dayworks only between the hours of 7 am and 5 pm Monday to Friday. If required, work may be undertaken on weekends between the same hours.
Activities include:
- demolition, excavation and transportation of materials using bobcats, excavators and small trucks
- fencing of worksites and installation of tree protection fencing
- small diggers and front loaders for importing and placing soil, trees and plants into garden beds
- trucks and cranes for installation of new streetlighting columns
- concrete/asphalt trucks for installation of paths, walls, crossings, kerbs and islands
- construction of retaining walls and paving that will include site cutting activities.
Tree removal activities
There is some tree removal to be undertaken as part of this project. In total there will be 15 trees removed. In their place, 12 new trees will be planted. These will be advanced size as opposed to saplings. In addition to tree planting, more than 2,200 plants will be planted within the new, widened verge. These will be a variety of grasses, shrubs, groundcovers and macrophytes.
Traffic and pedestrian access
There will be temporary changes for road users and pedestrians during these works. Access along shopfronts will be maintained at all times, however the works will require temporary fencing to ensure the safety of both our workers and the community.
There will be closures of Hardwick Crescent during construction within the two stages. Signed detours will be in place to redirect road users during this time. In addition, some existing on-street parking will be unavailable during the construction period to allow upgrades to be undertaken.
To facilitate the parking improvements, temporary closures of small sections of the surface carparks will be required. This will ensure works can be completed as quickly and safely as possible. These closures will be short-term, a maximum of one-week, to allow line marking machines access to the area.